Dynamics 365 Supply Chain supplier delivery-date tracking

Show the date history beside the quantity

Date tracking is more useful when a partial receipt does not disappear into a complete status. The scorecard pairs each date with quantity and leaves an unconfirmed balance visible.

The practical sequence is: retain the requested date, record each supplier promise, attach receipts to quantities, and show the balance that still needs a date. A transparent denominator keeps the result reviewable.

Worked fictional example

The following is sample/fictional data for a Microsoft Dynamics 365 Supply Chain workflow. It is not a customer result or a live ERP record.

FieldExample
PO lineD365-PO-4310 / 8
Requested / confirmed2026-10-22 / 2026-10-24
Receipt60 on 2026-10-24
Open balance40
Scorecard stateConfirmed date met for 60; 40 still unconfirmed

The browser artifact, Dynamics Supply Chain promise-date scorecard, gives this example a concrete review surface. It can show a parsed reply, draft an acknowledgment, calculate a date score, validate an export, or map a no-login route depending on the page. The artifact does not grant ERP access or silently change a promise date.

Evidence boundary

Public vendor and category documents describe procurement concepts and supplier-facing patterns. They do not prove that Helios has a live Microsoft Dynamics 365 Supply Chain connector. Any such connector is unverified. Keep the source export, review decision, and date change visible to the person who owns the PO.

Working artifact · fictional sample data

Supplier OTD scorecard

Runs in your browser
78.3%on-time / confirmed lines
92%lines with a status
25sample PO lines

Definition used here: receipt on or before the unmodified supplier promise date ÷ confirmed receipt lines. This sample is not an industry benchmark.

Sources and verification

Frequently asked questions

Does this use a Dynamics 365 metric?

No. It is a fictional, editable definition for a browser artifact. It is not a Dynamics report or benchmark; connector status is unverified.

What data should be real in a pilot?

Use an approved export and label every sample row. Agree on identifiers, date basis, partial-quantity rules, redaction, retention, and owner before sharing production data.