A scorecard that can be challenged

“On time” is only useful when a buyer can reproduce it. In this sample, the score is on-time confirmed receipt lines ÷ confirmed receipt lines. Unconfirmed lines remain visible, and partials are a separate operational flag rather than a hidden pass or fail.

Edit the sample counts below. The calculation updates in your browser. It intentionally does not turn the ISM Supplier Deliveries Index into a percentage: ISM’s index is a diffusion signal where readings above 50 mean slower deliveries, not the share of orders received on time.

The checked-in Helios proof report also records why public award data cannot produce a universal supplier league table. PCB and Lincoln Electric provide useful published scorecard examples, but each company’s grace window, denominator, and cadence differ. Use this artifact to agree on definitions with a supplier, not to issue a certification.

Once definitions are agreed, prepare the source export and check the connector route.

Working artifact · fictional sample data

Supplier OTD scorecard

Runs in your browser
78.3%on-time / confirmed lines
92%lines with a status
25sample PO lines

Definition used here: receipt on or before the unmodified supplier promise date ÷ confirmed receipt lines. This sample is not an industry benchmark.

Sources and verification

Frequently asked questions

What is the denominator in this example?

On-time confirmed receipt lines divided by all confirmed receipt lines. Unconfirmed lines are shown separately and are not silently counted as on time.

Is this an industry benchmark?

No. The rows and rates are fictional. Public scorecards demonstrate different definitions, so a comparison needs the promise-date rule, grace window, exclusions, and cadence alongside the percentage.