Automotive manufacturing supplier on-time delivery tracking

The decision for this workflow

Score each release line against its first committed date, then show revised dates as a change signal. The page uses sample/fictional data so a team can challenge the rule before sharing a real export. It is aimed at a buyer deciding what to ask, what to hold, and what to leave for a human.

Release-level OTD scorecard

This page’s working artifact is a Release-level OTD scorecard. It is intentionally narrower than a full ERP rollout: the buyer supplies a reviewed export or copies a supplier message, then checks the proposed state before anything is sent or written back.

Worked fictional example: Fictional four-release brake-hardware sample

FieldFictional value
On time18 of 24 confirmed lines
Date changed3 lines moved before due date
Late2 lines missed the first promise
Unknown1 line has no acknowledgment

The useful decision is score each release line against its first committed date, then show revised dates as a change signal. In a real review, record the source file, message date, reviewer, and any redaction before treating a value as operational.

What Helios does directly

Helios calculates the displayed example from supplied rows and preserves the date-change state for a buyer conversation. Helios keeps the distinction between a draft, an extracted value, and a buyer-approved decision visible. A supplier reply is not sent automatically from this page, and no ERP record is changed by this artifact.

Evidence boundary

This is a transparent sample definition, not a customer KPI, industry target, or automotive certification. The three sources below provide industry or vendor context; they do not establish a Helios customer result, certification, or live integration. The p1-stores status is the controlling integration boundary for this wave: 0 live-tested integrations.

Use the related workflow links to prepare the minimum export, draft an acknowledgment, or review a supplier reply. Keep real purchase orders and controlled documents in the approved environment.

Working artifact · fictional sample data

Supplier OTD scorecard

Runs in your browser
78.3%on-time / confirmed lines
92%lines with a status
25sample PO lines

Definition used here: receipt on or before the unmodified supplier promise date ÷ confirmed receipt lines. This sample is not an industry benchmark.

Sources and verification

  • AIAG quality resources (primary; accessed 2026-10-23) — AIAG provides automotive quality context; it is not a Helios customer or performance reference.
  • NHTSA vehicle safety overview (primary; accessed 2026-10-23) — NHTSA explains safety obligations and context; it does not support an integration or certification claim.
  • SourceDay PO collaboration datasheet (primary; accessed 2026-10-23) — SourceDay describes a category workflow; its features and results are not attributed to Helios.

Frequently asked questions

Why retain an earlier promise date?

It makes schedule changes visible. A revised date can be operationally useful while still showing that the first commitment changed.